Work Order #6173

Install a completely new cable directly from the meter to the electrical board, running down the slope.

Includes supplying and installing the required materials (cable, pipe and other associated materials).

Breaking the meter box and cementing it to secure the new pipe in place.

Installation of the new pipe and cable above ground, drilling the wall if necessary to bring the cable into the property, although the existing access point may be used if suitable.